Question No : 1


Which 2 actions should the Workshop Facilitator take to implement the new Must Have requirement?

정답:

Question No : 2


Which 2 actions should the Technical Coordinator take to implement the new Must Have requirement?

정답:
Explanation:
To implement the new Must Have requirement for financial transaction functionality on the coffee shop insurance product website, the Technical Coordinator should focus on actions that align with their role in overseeing the technical aspects of the project.
The following actions are most appropriate for the Technical Coordinator:
Selected Actions for the Technical Coordinator:
A. Ensure that the latest version of the website design in the Solution Architecture Definition is provided to all members of the Solution Development Team.
E. Check for any documented standards which need to be applied to the development of online financial transaction functionality.
A. It's crucial for the Technical Coordinator to ensure that the Solution Development Team has access to the most current website design specifications, especially when new functionalities are being added. This ensures consistency and alignment with the overall solution architecture, facilitating effective and efficient development.
E. The Technical Coordinator is responsible for ensuring that all technical aspects of the project adhere to relevant standards, including those related to online financial transactions. This involves identifying, understanding, and applying any necessary regulatory, security, and technical standards to the development process, ensuring compliance and functionality.
Why Other Actions Are Less Suitable:
B. Assessing the impact on the original Business Case is typically the responsibility of the Business Sponsor or Project Manager, as it involves financial and strategic considerations beyond the Technical Coordinator's primary focus.
C. Adding tasks to the Timebox Plan is generally a responsibility shared between the Project Manager and the Solution Development Team, with the Technical Coordinator providing input on technical feasibility and requirements.
D. Consolidating and circulating an agenda for the workshop is an important logistical task but may not directly fall under the Technical Coordinator's responsibilities. This task is often handled by the Project Manager or a designated administrative role.

Question No : 3


Which 2 actions should the Project Manager take to implement the new Must Have requirement?

정답:
Explanation:
To effectively implement the new Must Have requirement for financial transaction functionality on the coffee shop insurance product website, the Project Manager should focus on actions that align with their role in planning, execution, and team coordination.
The following actions are most appropriate for the Project Manager:
Selected Actions for the Project Manager:
B. Add the tasks required to develop the new financial transaction functionality to the Delivery Plan.
C. Update the Delivery Plan to show the new financial transaction functionality as a deliverable.
B. Integrating the tasks necessary for developing the new functionality into the Delivery Plan is crucial. This ensures that all project activities are accounted for and scheduled, which helps in managing the project's timeline and resources effectively.
C. Reflecting the new financial transaction functionality as a deliverable in the Delivery Plan is important for clarity and focus. It signifies the inclusion of this functionality as a critical component of the project's scope, guiding the team's efforts and priorities.
Why Other Actions Are Less Suitable:
A. While ensuring adherence to documented standards is important, it is typically a collaborative effort involving the Technical Coordinator and Solution Development team, in addition to the Project Manager, to ensure technical compliance.
D. Sourcing and hiring specific expertise, such as a web developer skilled in online financial transactions, is indeed part of the Project Manager's responsibilities. However, the actions related to the Delivery Plan (options B and C) are more directly aligned with the immediate steps for implementing a new requirement in the project's scope.
E. Consolidating and circulating an agenda for the workshop is a logistical task that the Project Manager might oversee or delegate. However, the actions related to planning and updating the Delivery Plan are more critical to the successful implementation of the new requirement.

Question No : 4


Which 2 actions should the Business Visionary take to implement the new Must Have requirement?

정답:
Explanation:
To implement the new Must Have requirement for the coffee shop insurance product website with financial transaction functionality, the Business Visionary should focus on actions that align with their role in guiding the project's vision and ensuring it meets business needs.
The following actions are most appropriate for the Business Visionary:
Selected Actions for the Business Visionary:
A. Send a company-wide communication to explain the implications of the business change to all interested parties.
D. Ensure the marketing and sales teams are working together to deliver the most effective outcome.
A. As a Business Visionary, communicating the implications of significant business changes, such as the introduction of a new financial transaction functionality, is crucial. This helps in aligning all parts of the organization with the project's objectives and the strategic direction, ensuring everyone understands the change and its benefits.
D. The Business Visionary plays a key role in ensuring that different departments, such as marketing and sales, collaborate effectively to support the project's objectives. By ensuring these teams work together, the Business Visionary helps in maximizing the project's impact and effectiveness in meeting business goals.
Why Other Actions Are Less Suitable:
B. Assessing the impact of new requirements on the Business Case is important, but it's typically a responsibility shared with the Business Sponsor, who has a more direct role in managing the project's financial and strategic alignment.
C. Sourcing and hiring technical expertise is generally a task for the Project Manager or technical leads. The Business Visionary's role is more focused on strategic oversight rather than operational tasks.
E. Organizing and managing workshop details, such as circulating an agenda, might be supported by the Business Visionary, but it's often a task handled by the Project Manager or a designated coordinator to ensure efficient planning and execution of project activities.

Question No : 5


Answer the following questions about actions to be taken by different roles.
The Business Sponsor has decided that the new coffee shop insurance product website pages will include the financial transaction functionality to support the end-to-end sales process. The Business Sponsor views this as a valuable sales tool, enabling customers to pay for insurance policies online. If successful, this new financial transaction functionality is to be made available across all other insurance products. This is a new Must Have requirement.
All parties are to be invited to a workshop to discuss the additional work required to deliver the required solution including the new Must Have requirement. The areas to be discussed include specialist skills required and possible legal, financial and technical standards to be adhered to.
Remember to limit your answers to the number of selections requested in each question.
Which 2 actions should the Business Sponsor take to implement the new Must Have requirement?

정답:
Explanation:
To implement the new Must Have requirement for the coffee shop insurance product website, which includes financial transaction functionality, the Business Sponsor should take the following actions:
Selected Actions for the Business Sponsor:
B. Check the viability of the project, following the inclusion of the new Must Have requirement.
E. Assess the impact of the new Must Have requirement on the original Business Case.
B. Evaluating the project's viability after adding a significant new requirement is crucial. This involves analyzing whether the project can still meet its objectives within the given constraints, such as time, budget, and resources, especially when the new requirement could potentially add complexity and cost.
E. Understanding how the new requirement affects the original Business Case is essential. This involves reassessing the project's expected benefits, costs, and risks in light of the new functionality. It ensures that the project remains aligned with business objectives and continues to offer a viable return on investment.
Why Other Actions Are Less Suitable:
A. While ensuring adherence to relevant standards is important, it is more of a task for the technical team or a specific role such as the Technical Coordinator, rather than the primary responsibility of the Business Sponsor.
C. Sourcing and hiring specific technical expertise, such as a web developer with experience in online financial transactions, is generally a responsibility delegated to the Project Manager or relevant technical leads, not the Business Sponsor directly.
D. While communicating business changes to all interested parties is important, the specific action of explaining the implications of the business change company-wide is more likely to be a collaborative effort involving several roles, including the Business Change Manager, rather than solely the Business Sponsor's responsibility.

Question No : 6


The Business Ambassador assigned to the project is only available 2 days a week. The Project Manager has stated that the Investigation stage for each Timebox should, where possible, be planned around the availability of the Business Ambassador.
Is this an appropriate application of the DSDM lifecycle?

정답:
Explanation:
In the context of the DSDM lifecycle, the Investigation stage of a Timebox is crucial for understanding and defining the work to be done, which often necessitates close collaboration with business representatives such as the Business Ambassador. This role is integral in ensuring that the project's outputs align with business needs and priorities. Planning the Investigation stage around the Business Ambassador's availability facilitates this essential engagement, making it a suitable application of the DSDM lifecycle. This approach ensures that the project benefits from the Business Ambassador's insights and guidance during critical early phases, contributing to a stronger alignment between project deliverables and business requirements.
Reference: The Agile Project Management (AgilePM®) framework, which incorporates DSDM principles, emphasizes the importance of collaboration between the project team and business stakeholders throughout the project lifecycle. The involvement of the Business Ambassador during the Investigation stage is particularly valuable for clarifying requirements, setting priorities, and ensuring that the project remains focused on delivering business value, in line with Agile and DSDM practices.

Question No : 7


Answer the following questions about the DSDM Lifecycle.
Decide if each observation is an appropriate application of Agile Project Management for this project and select the option that supports your decision.
When the project was in the Feasibility phase it was initially proposed by the Finance Manager that it was a fixed price for a fixed specification' project. The Project Manager has decided that the best way to tackle it would be to leave the development of the least valuable features of the product until last.
Is this an appropriate application of the DSDM lifecycle?

정답:

Question No : 8


Resources are limited. The Sales Manager has two marketing assistants who may be able to give a few hours a week between them to the project.
What action should the Project Manager take?

정답:
Explanation:
In the context of Agile Project Management, it is crucial to have clear commitments regarding team members' availability to ensure that project planning and execution can be as accurate and effective as possible. By securing a formal agreement on the hours the marketing assistants can dedicate to the project each week, the Project Manager can better plan tasks and allocate resources, thereby optimizing the team's capacity and ensuring that project timelines and deliverables are realistic and achievable.
Reference: The Agile Project Management (AgilePM®) framework emphasizes the importance of clear communication, resource planning, and commitment from all team members to ensure project success. Having a formal agreement on availability helps in setting clear expectations and allows for more effective planning and utilization of resources within the constraints of the project, aligning with Agile principles of collaboration, adaptability, and iterative progress.

Question No : 9


An external web developer is to be contracted to create the new coffee bar insurance area on the existing web site. The chosen web developer will only agree to work on a 'fixed price for a fixed specification' contract.
What action should the Project Manager take?

정답:
Explanation:
Dividing the work into smaller, well-defined component parts is a strategic approach when dealing with fixed-price contracts within an Agile framework. This method allows for greater flexibility and adaptability, as each component can be specified in detail, making it clear what the external web developer is responsible for delivering. This approach aligns with Agile principles by enabling incremental development and delivery, allowing for adjustments and refinements to be made as the project progresses and more information becomes available.
Reference: In Agile Project Management, particularly when incorporating external resources or contractors, breaking down the project into smaller, manageable parts is a common practice. This not only facilitates better control and tracking of progress but also ensures that the project remains adaptable, with the capacity to respond to changes in requirements or priorities. This approach is in line with Agile methodologies that emphasize iterative development, customer collaboration, and responding to change over following a fixed plan.

Question No : 10


The Marketing Director has insisted that detailed requirements for the new coffee bar insurance web pages should be clearly defined in the early phases of the project.
What action should the Project Manager take?

정답:

Question No : 11


Time is running short and the Must Have requirements for the data entry screen of the web page, as recorded in the Prioritised Requirements List, are not going to be completed on time.
What action should the Project Manager take?

정답:

Question No : 12


Several of the web developers working on the project have no Agile experience. When answering the questions in the Project Approach Questionnaire (PAQ), the Project Manager could not agree with the statement 'all members of the project understand and accept the DSDM approach'.
What action should the Project Manager take?

정답:

Question No : 13


Which 2 statements represent appropriate entries for the plan for Post-Project activities?

정답:
Explanation:
For the XAN Insurance Company Web Project, the plan for Post-Project activities should include actions and measures that will be undertaken after the project's deliverables have been implemented to ensure sustained benefits, monitor performance, and facilitate continuous improvement.
Selected Statements for the Plan for Post-Project Activities:
D. A report showing the number of application forms completed online through the website for coffee shop insurance policies will be produced weekly.
E. Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
D. Producing a weekly report on the number of application forms completed online is a clear post-project activity. It provides ongoing monitoring of the project's impact and the effectiveness of the online system in attracting coffee shop insurance policies.
E. Comparing the processing times of online sales to telephone sales after the new system's deployment is an essential post-project activity. It evaluates the efficiency and effectiveness of the new online system, offering insights into improvements and adjustments that may be needed.
Why Other Statements Are Excluded:
A. Creating a company-wide email to show the number of policies sold by each sales assistant weekly is more related to internal sales performance monitoring and motivation rather than a specific post-project activity tied to the project's objectives.
B. Circulating a copy of the revised sales procedure before product deployment is a preparation step for the transition to the new system, rather than a post-project activity.
C. The Project Manager attending Daily Stand-up meetings is part of the ongoing project management and team coordination activities during the project, not a post-project activity.

Question No : 14


Which 2 statements represent appropriate entries for the Development Approach Definition?

정답:
Explanation:
For the XAN Insurance Company Web Project, the Development Approach Definition document should outline the methodologies, tools, and techniques to be used during the development process of the project. It focuses on how the project will be executed in terms of technical and management practices.
Selected Statements for the Development Approach Definition:
C. An easy to use web development tool called 'WebMatrix' is to be used to develop and maintain the website extension.
E. Accessibility and performance of the new online quotation area is to be tested using a tool called Sitebeam.
C. This statement directly specifies a tool (WebMatrix) that will be used for web development and maintenance in the project. It is a clear choice regarding the technical approach and infrastructure, making it suitable for inclusion in the Development Approach Definition.
E. Mentioning Sitebeam as a tool for testing accessibility and performance outlines specific methods for ensuring quality and usability in the development process. It provides actionable information on how testing will be conducted, fitting the criteria for the Development Approach Definition.
Why Other Statements Are Excluded:
A. Introducing an awards or bonus scheme to create competition among sales assistants pertains more to internal sales team management and motivation strategies rather than the technical or methodological approach to developing the project.
B. Comparing traditional telephone sales with online sales is related to the project's performance measurement and post-implementation review, not the development approach or methodology used during the project.
D. The request from the Finance Director for a detailed cost report is related to project financial management and monitoring. While important, it does not detail the technical or methodological approach to developing the project's deliverables.

Question No : 15


Which 2 statements represent appropriate entries for the Prioritised Requirements List?

정답: