Planning & Scheduling Professional (PSP) Exam 온라인 연습
최종 업데이트 시간: 2024년11월08일
당신은 온라인 연습 문제를 통해 AACE AACE-PSP 시험지식에 대해 자신이 어떻게 알고 있는지 파악한 후 시험 참가 신청 여부를 결정할 수 있다.
시험을 100% 합격하고 시험 준비 시간을 35% 절약하기를 바라며 AACE-PSP 덤프 (최신 실제 시험 문제)를 사용 선택하여 현재 최신 120개의 시험 문제와 답을 포함하십시오.
/ 3
Question No : 1
Which of the following phases does NOT describe the commonly accepted construction life cycle?
정답:
Question No : 2
Which statement is true?
정답:
Question No : 3
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay.
Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
정답:
Question No : 4
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
정답:
Question No : 5
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity
정답:
Question No : 6
In its simplest form, what is the main drawback of critical path method scheduling?
정답:
Question No : 7
The amount of time that an activity can be delayed from its early start date without delaying project completion is called
정답:
Question No : 8
Each of the following accurately describes total float in a schedule EXCEPT:
정답:
Question No : 9
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
정답:
Question No : 10
All the following describe the critical path of a schedule EXCEPT:
정답:
Question No : 11
Project delays are best analyzed
정답:
Question No : 12
When resource leveling craft labor for a critical path schedule, the scheduler
정답:
Question No : 13
Resource planning must take all of the following into account except for
정답:
Question No : 14
Under which circumstance should one perform resource-leveling calculations?
정답:
Question No : 15
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?