당신은 온라인 연습 문제를 통해 Adobe AD0-E903 시험지식에 대해 자신이 어떻게 알고 있는지 파악한 후 시험 참가 신청 여부를 결정할 수 있다.
시험을 100% 합격하고 시험 준비 시간을 35% 절약하기를 바라며 AD0-E903 덤프 (최신 실제 시험 문제)를 사용 선택하여 현재 최신 70개의 시험 문제와 답을 포함하십시오.
정답:
Explanation:
To provide a list of all projects for a specific company (Acme) and group (Marketing), the correct approach is to filter by both Company ID and Group ID in the custom project report. This allows the project manager to isolate projects related to Acme Company that the Marketing Group is responsible for.
정답:
Explanation:
In Workfront, creating a program-specific dashboard allows for the presentation of real-time data to stakeholders. Additionally, automated reports can be set to send out weekly, meeting the requirement for a consistent recap. This automation reduces the manual effort of downloading and sending reports each week.
정답:
Explanation:
In Workfront, billing rates can be customized for individual projects. To apply a negotiated rate for the Video Editor role within a specific initiative, the project manager can add a new billing rate at the project level. This ensures that the rate is applied only to tasks within the project and does not affect the default system-wide rate for other projects.
정답:
Explanation:
To create a custom report in Workfront that focuses on issues logged to projects, the project manager needs to create a new Issue report from the Reports page. By applying a filter based on the Project Owner ID and grouping the report by project name, they can track all the issues associated with the projects they own. This approach provides clear visibility into project-related issues.
정답:
Explanation:
In Workfront, when a task owner is unavailable due to time off, they can update the Commit Date to reflect when they are available to work on the task. This prevents delays and ensures the task is completed within a revised timeline. The Commit Date feature is designed to accommodate personal
schedules and ensure tasks are accurately tracked without putting the task "At Risk" unnecessarily.
정답:
Explanation:
When reducing the task duration and distributing the work among multiple users, changing the Task Duration Type to "Calculated Work" allows Workfront to automatically adjust the duration based on the number of assignees (in this case, 4 users). This will enable the task to be completed within the new shorter timeframe without adjusting the total planned hours.
정답:
Explanation:
In Workfront, setting the correct task constraint and planned hours ensures that the task starts on the intended date (September 23) and allows the team to track the time allocated (10 hours) over a 2-week duration. "Must Start On" ensures the task begins exactly on the planned start date.
정답: C
Explanation:
In Workfront, when adjusting user access, it’s important to ensure that Program Manager A only has the necessary level of access to their own program. To rectify the over-access issue, the portfolio manager must share the relevant program with Program Manager A with the correct Manage access and remove their broader Manage access to the portfolio. This restricts their control to only their specific program.
정답:
Explanation:
In Workfront, a "Program" is used to group related projects that share a common objective or need to be tracked together, such as adherence to budget and timeline. Programs allow for collective reporting on these projects, making it easier for team leads to monitor progress, manage resources, and report on key performance indicators (KPIs) across multiple projects.
정답:
Explanation:
In Workfront, if a task that is part of the critical path is delayed, it affects the overall project schedule. Even though the task is not overdue yet, Workfront's automated system flags the project as "At Risk" if there is a delay in progress that could impact the project's timeline. This "At Risk" condition acts as a warning to project managers and stakeholders that immediate attention is needed.
정답:
Explanation:
In Adobe Workfront, risks associated with a project should be logged as part of the project business case. The "Risk" section within the business case allows stakeholders to document any potential threats to the project timeline, scope, or resources. Identifying this risk as a "schedule" risk helps communicate the potential delay to the project stakeholders and allows it to be tracked and mitigated effectively.
정답:
Explanation:
In Workfront, custom data fields created for projects are typically found within the "Business Case" section, specifically under "Project Info." This area houses key project information and unique
custom fields that are relevant to the project's setup. The "Project Details" section is more focused on task-related information and the overall summary of the project.
정답:
Explanation:
In Workfront, users with "Contribute" access are typically able to modify and interact with content but are not allowed to perform higher-level administrative tasks like attaching templates or adding tasks. Adding a custom form is within the scope of what a user with Contribute access can do, as it involves adding data input fields to an existing project.
정답:
Explanation:
In Adobe Workfront, the "Assignments" field allows a project manager to see all the users assigned to a task. This field is useful for viewing multiple assignees on a single task, as tasks can have more than one person responsible. The "Assigned To" and "Assigned" fields are often used for single-user assignments and are not as comprehensive for viewing all task assignees.
정답:
Explanation:
For executive-level reporting, a program report grouped by department provides a holistic view of ongoing initiatives. This includes the health of programs, urgency, and alignment with business goals. This type of report is essential for leadership teams to assess overall performance and make informed decisions that align with the company’s strategic objectives.