Question No : 1
A design build firm has been retained by a client to construct an outpatient clinic. The client has hired an ICT distribution designer to review the DB firm's work product ensuring that
the certified (mat documents are complete.
In what capacity would the designer MOST LIKELY be serving?

正解:

Question No : 2
A program manager is developing a program management plan by integrating the plans of constituent projects. During this effort, the program manager learns that a resource is critical to more than one component and there is a time overlap for their availability
When creating the program resource management plan, what should the program manager do first?

正解:

Question No : 3
A program to implement a company's new system is nearing completion and the program manager attempts to close the program However, despite training provided to the operational staff on the new system, there is concern that the defined expected benefits will not be fully realized.
To prevent this concern in the future, which of the following should occur?

正解:

Question No : 4
The type of apparatus housed in ERs vary greatly in size, purpose and function.
Which two of the following active equipment is included? (Choose two.)

正解:

Question No : 5
An ICT distribution designer installed a 50/1 ?5 mm/1300 nm fiber optic cable from Building A to identical Building B with a distance of 600 m (1968 ft) At Building B. the designer fusion splice this new cable to an existing identical 50/126 mm fiber optic cable that runs 800 m (2525 ft) to Building C. Both ends are terminated with SC connectors.
What is the loss budget for the above fiber link?

正解:

Question No : 6
The transfer of unwanted signals may occur over one path or several paths.
What method addresses the mitigation or suppression of unwanted signals?

正解:

Question No : 7
When sizing an underground entrance facility, what is the MINIMUM amount of 103 metric designator conduits (4 trade size) that should be specified by the ICT distribution design?

正解:

Question No : 8
XYZ Company hires you to make its transitioning procedure more effective in meeting close-out requirements. You review XYZ's transitioning procedures to eliminate any that do not belong in the close-out phase.
Which of the following procedures should you removed?

正解:

Question No : 9
Coupling with electrical circuits can create inductive interference to telecommunications facilities.
Which of the following can decrease the coupling effect?

正解:

Question No : 10
The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B.
This is an example of which of the following?

正解:

Question No : 11
The program manager has a global program with live component projects. The program sponsor wants the management plans, processes/procedures and technology to be uniform across the program. The requirements will create issues and result in increased costs. The program sponsor is new and has imposed these new requirements six months into a three-year program.
What should the program manager do next?

正解:

Question No : 12
Near the completion of a transformation program, the operations manager is concerned that their department failed lo be notified in advance of the new service being transitioned into operations. They claim that their department did not approve this service and is now unprepared and untrained to support the transformation.
What should the program manager have done first to prevent this?

正解:

Question No : 13
Which of the following terms is often used to describe two parallel paths that have identical conductive terminations to two separate grounding reference points?

正解:

Question No : 14
An ICT distribution designer is designing a backbone cabling network that is specified for a campus network including several links approaching 2000 m (6562 It) and data rates of 100 Gb/s
What optical fiber type(s) should be used?

正解:

Question No : 15
A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue.
What should the program manager do NEXT?

正解: