SAFe 5 Advanced Scrum Master 온라인 연습
최종 업데이트 시간: 2024년11월08일
당신은 온라인 연습 문제를 통해 Scrum SASM 시험지식에 대해 자신이 어떻게 알고 있는지 파악한 후 시험 참가 신청 여부를 결정할 수 있다.
시험을 100% 합격하고 시험 준비 시간을 35% 절약하기를 바라며 SASM 덤프 (최신 실제 시험 문제)를 사용 선택하여 현재 최신 180개의 시험 문제와 답을 포함하십시오.
정답:
Explanation:
Scrum Master should attend Scrum of scrums as participant, rest Iteration review and DSU is facilitated by SM.
정답:
Explanation:
The antipatterns are:
정답:
Explanation:
Relentless improvement can be best drived by Iteration Retrospective and Inspect and adapt event.
정답:
Explanation:
Scrum is a FRAMEWORK which is best suitable for Team.
정답:
Explanation:
Enterprises decide to embrace Lean-Agile development either because their existing processes aren’t producing the results they need, or because they anticipate that they won’t in the future. By choosing a Lean-Agile path, they’re embracing a model based on incremental development and early and continuous value delivery. Continous value delivery will create ability to deliver early and often has a direct economic benefit.
정답:
Explanation:
Agile teams often use 'estimating poker,' which combines expert opinion, analogy, and disaggregation to create quick but reliable estimates. Disaggregation refers to splitting a story or features into smaller, easier to estimate pieces. And firstly Implement the 'happy path' and the rest of the scenarios afterwards.
정답:
Explanation:
Achieving the goals of Release on Demand requires an understanding of how to decouple the release from deployment.
정답:
Explanation:
Bug Stories are difficult to complete in one iteration.
정답:
Explanation:
Kanban systems are the primary mechanism to achieve SAFe Principle #6 C Visualize and limit WIP, reduce batch sizes, and manage queue length.
정답:
Explanation:
teration planning is ideally done with the entire team in a meeting, including key stakeholders, typically lasting one to a few hours, at the beginning of an iteration. This ensures that the entire team understands what needs to be done, and they commites the plan.
정답:
Explanation:
For one iteration One team member's capacity is 8, and if any holiday or trainings are there then we have to deduct 1 day from each team members capacity.
정답:
Explanation:
All ART stakeholders participate along with the Agile Teams in the I&A event. The result is a set of improvement backlog items that go into the Program Backlog for the next PI Planning event. In this way, every Agile Release Train (ART) improves every PI.
정답:
Explanation:
Transparency means clear and transparent current process and updates should be visible to everyone.
정답:
Explanation:
Sometimes Team needs proper guidance and support if it lacks team may not reach that phase.
정답:
Explanation:
When issues have been identified, root cause analysis is performed, potential corrective actions are discussed, and improvement Stories are entered into the Team Backlog.